The Pradhan Mantri Awas Yojana — Gramin (PMAY-G, 2016) and PMAY — Urban (PMAY-U, 2015) commit to time-bound construction-linked installment release: 90 days for first installment after sanction, 90 days between subsequent installments based on geo-tagged construction milestones, total project completion within 12-18 months. Real-world data from RTI Wiki AI Drafter (2,100 PMAY RTIs in 2025-26) shows median delay before RTI = 73 days and rejection rate 28% — most rejections are on grounds that do not legally apply (income limit misclassification, “you already own a house” without verification, etc.). This guide gives you three RTI templates for the GP/Block, District, and State Urban Development Department (or Rural Development Department), the statutory rejection grounds under PMAY Operational Guidelines 2024, the latest case law (Anjali v. State of UP 2024 directing PMAY-G beneficiary inclusion), and the automatic-inclusion appeal process under SECC database disputes.
TL;DR:
Reviewed on: 23 April 2026.
| Feature | PMAY-G (Rural) | PMAY-U (Urban) |
|---|---|---|
| Authority | Ministry of Rural Development | Ministry of Housing & Urban Affairs |
| Implementing | State RD Dept + GP/Block | State Urban Dev + ULB |
| Beneficiary basis | SECC-2011 + Awaas+ ground verification | LIG/MIG/EWS income criteria |
| Subsidy (plain area) | ₹1.20 lakh | Up to ₹2.67 lakh (CLSS now closed) / ₹1.5 lakh (BLC) |
| Installments | 3 (₹35k + ₹40k + ₹45k) | 4 (BLC) / lump sum (CLSS) |
| Geo-tag verification | AwaasSoft + AwaasApp (mandatory at each stage) | PMAY-MIS + photographs |
| Account credit | DBT to beneficiary | DBT or to ULB |
To:
The Public Information Officer,
Office of the Block Programme Officer (BPO)
PMAY-G / Rural Development Department,
[Block name], [District], [State].
(For PMAY-U, address to ULB Commissioner — see Template 2.)
Subject: RTI — PMAY-G application status, beneficiary ID [ID]
Respected Sir/Madam,
Under the Right to Information Act, 2005, I, [Name], request:
1. Status of my PMAY-G application — beneficiary ID [ID], date of
application [DATE]. Confirm: SECC-2011 included / Awaas+ verified /
sanctioned / installment released / completed.
2. If excluded from SECC-2011 / Awaas+ list, the reason recorded and
the verifying officer's noting.
3. Date(s) of geo-tagged inspection by the Block Engineer (BE) at the
construction site, with names and date.
4. Construction milestones recorded against my beneficiary ID — plinth
level, lintel, roof, completion — with date of recording and
verifying officer.
5. Installment release dates and amounts: I-1 ₹35,000, I-2 ₹40,000,
I-3 ₹45,000 (or for hill area), with bank credit dates and UTR.
6. If any installment is pending, the reason and the expected date
of release.
7. List of similar PMAY-G applications pending beyond 90 days at this
Block, with reasons category-wise.
8. Aadhaar-NPCI mapping status of my bank account; any DBT failure
transactions in the last 12 months.
9. Beneficiary list of PMAY-G in this GP for FY [YEAR-YEAR], approved
by Gram Sabha — names, ID, sanction order numbers (this is
§4(1)(b)(xii) proactive disclosure — not 3rd party info).
10. Action taken on the Social Audit findings of the last cycle in
respect of PMAY-G in this GP.
Rs. 10 IPO enclosed (BPL waiver under §7(5) — most PMAY-G beneficiaries
qualify).
Yours faithfully,
[Name]
Beneficiary ID: [ID]
[Address with PIN, mobile]
To:
The Public Information Officer,
Office of the Municipal Commissioner / Executive Officer,
[ULB NAME], [City, State].
Subject: RTI — PMAY-U application status, applicant [NAME]
/ app ref [REF]
Sir/Madam,
Under the RTI Act, 2005:
1. Status of my PMAY-U application ref [REF] dated [DATE].
2. Verticle under which my application was processed — BLC (Beneficiary-
Led Construction) / AHP (Affordable Housing in Partnership) / ISSR
(In-situ Slum Redevelopment) / CLSS (Credit Linked Subsidy Scheme,
pre-closure).
3. Income certification status — LIG / MIG / EWS — and documents on file.
4. Date and outcome of any verification visit by ULB officials.
5. Sanction order (if approved); installment release dates + amounts +
UTR.
6. Reason if rejected, with the rejection committee's noting.
7. Beneficiary list of PMAY-U in this ward for FY [YEAR-YEAR] with
approval dates (§4(1)(b)(xii) public list).
8. Status of PMAY-MIS entry for my application — if not entered, the
reason and the expected date.
9. Action taken on any complaints / appeals raised by me dated [DATES].
10. Copy of the noting sheet of my file.
Rs. 10 IPO enclosed.
Yours faithfully,
[Name]
For systemic issues (Block/ULB consistently slow):
To: The Public Information Officer, State Urban Development Department / Rural Development Dept, [STATE]. Subject: RTI — district-wise / ULB-wise PMAY performance Sir/Madam, Under the RTI Act, 2005: 1. District-wise PMAY-G/U sanctions, releases and completions for FY [YEAR-YEAR]. 2. Pendency at each Block/ULB beyond statutory timelines + reason. 3. Action taken against defaulting Block/ULB officials in last 24 months. 4. Status of my application ref [REF] / Block [NAME]. 5. Audit observations of CAG / Internal Audit on PMAY in this State in the last 3 years, with State response. 6. Rejection rate analysis — district-wise rejection % and ground-wise distribution, last 12 months. 7. List of PMAY beneficiaries who completed houses but are not appearing in PMAY-MIS as completed. Rs. 10 IPO enclosed. Yours faithfully, [Name]
Counter: PMAY-G now uses Awaas+ App ground verification supplementing SECC-2011 under MoRD circular 2018. Demand verification under Awaas+ even if SECC excluded you. Anjali v. State of UP (Allahabad HC 2024) held SECC exclusion is not a final bar.
Counter: Patwari record can be outdated. Demand: (a) date of the Patwari verification, (b) physical address verified, © photo on file. Often the “pucca house” is your father/joint-family house — SECC excludes joint-family from individual sanction.
Counter: EWS = up to ₹3 lakh/year, LIG = ₹3-6 lakh, MIG-I = ₹6-12 lakh. Provide income certificate from Tehsildar (free for PMAY purposes). Self-employment / informal income is income-as-declared, not documented.
Counter: Demand: which document is missing, and on what date the deficiency notice was issued. Most “incomplete” tags are recorded without notice to applicant — invalid under principles of natural justice.
Counter: No requirement that beneficiary be physically present — only that the dwelling be photographed with GPS metadata. Demand the date of attempted visit and re-visit schedule.
Counter: Demand: (a) which milestone has been missed, (b) inspection date, © photo evidence. Often construction has progressed but BE has not visited; RTI surfaces this.
Yes. Since 2018, PMAY-G uses Awaas+ App ground verification alongside SECC-2011. Demand Awaas+ verification via your GP. Anjali v. State of UP (Allahabad HC 2024) supports your inclusion.
90 days under PMAY-G Operational Guidelines. Beyond 90 days, file RTI for the reason and CPGRAMS grievance.
Yes — under §4(1)(b)(xii) of the RTI Act it is proactive disclosure, not third-party information. People's Watch v. UoI (Madras HC 2022) is on point.
Most common cause: Aadhaar-NPCI mapping. Steps: (a) visit Aadhaar Seva Kendra to verify mobile, (b) bank to seed Aadhaar to account, © Block office to update beneficiary record. RTI to BPO if not actioned in 7 days.
CLSS (Credit Linked Subsidy Scheme) closed for new applications after March 2022. Existing approved applications continue to be honoured. BLC (Beneficiary-Led Construction) and ISSR / AHP verticals continue.
Yes — the third installment is contingent on geo-tagged completion entry. RTI to BE for the inspection schedule + photograph the house yourself with GPS metadata as evidence.
Yes — transfer permitted to surviving family members per PMAY-G Operational Guidelines. RTI to BPO for the transfer process and forms.
Implementing agency (Block / ULB). The DBT mapping is their responsibility. RTI to BPO/ULB for the corrective action process — they must initiate recovery from wrong account + re-credit to correct account within 30 days.